Toondah Ferry Terminal Environmental Impact Statement.
Toondah Ferry Terminal Environmental Impact Statement.
Highlights:
The Project will result in the direct loss of marine and wetland habitat within the reclamation and dredging footprint including: 3.4 ha of mangroves; 37 ha of seagrass, including 11.8 ha in the Fison channel extension; and 8.8 ha of unvegetated sand/mud.
The existing trailer boat ramp will be removed and replaced by a facility for non-motorised vessels.
Link to summary
Executive Summary.pdf (caapp.com.au)
-
Ausfish Platinum Member
Re: Toondah Ferry Terminal Environmental Impact Statement.
Originally Posted by
Bobpen
Toondah Ferry Terminal Environmental Impact Statement.
Highlights:
The Project will result in the direct loss of marine and wetland habitat within the reclamation and dredging footprint including: 3.4 ha of mangroves; 37 ha of seagrass, including 11.8 ha in the Fison channel extension; and 8.8 ha of unvegetated sand/mud.
The existing trailer boat ramp will be removed and replaced by a facility for non-motorised vessels.
Link to summary
Executive Summary.pdf (caapp.com.au)
Gee 37ha of seagrass is a lot of seafood habitat gone for ever.