    North stradbroke Island Borefeild and Pipline

    Summary of proposed action
    NOTE: You must attach an A4 size map/plan(s) showing the location and approximate boundaries
    of the area in which the project is to occur. The summary below should encompass any alternative
    locations, timeframes or activities that are listed in Section 3.2.

    2.1
    Short description
    The project is to construct and have operation a new borefield and
    associated pipeline on North Stradbroke Island (NSI) (Figure 1) to
    pump groundwater into the South East Queensland regional water
    grid (Figure 2) via the Eastern Pipeline Interconnector (Figure 3)
    as part of the South East Queensland Regional Water Supply
    Strategy by 31 December 2008. The Southern Regional Water
    Pipeline Company Pty Ltd will be the proponent for the project and
    will implement the project on behalf of Redland Shire Council.
    2.2


    Latitude and longitude
    Latitude Longitude
    location point degrees minutes seconds degrees minutes seconds
    No final location for the borefield and pipeline has been decided.
    Location will be finalised through the assessment phase. Locations
    being considered are shown in Figures 4 and 5 (borefield) and
    Figures 6 and 7 (pipeline).
    2.3


    Locality
    The location of the borefield is not yet known, although locations
    currently under consideration are shown in Figures 4 and 5. The
    location of the borefield will be finalised during the assessment
    phase (refer Section 3.2).
    The pipeline route will traverse the island from the borefield, south
    to the current NSI Water Treatment Plant. The final alignment has
    not been decided. Three potential alignments (eastern, central and
    western) have been considered during the assessment phase with
    two ie. the Preferred Alignment and Alternative Alignment B, to be
    the subject of further environmental assessment.
    2.4


    Size of the development
    footprint or work area
    (hectares)
    This is to be determined. The size of the development will relate to
    the footprint of bores, associated pipe works and pumping stations.
    2.5


    Street address of the site
    N/A
    2.6


    Lot description
    Not known at this stage.
    Will be determined during the assessment phase.
    2.7


    Local Government Area and
    Council contact (if known)
    Redland Shire Council
    Contact: Troy Kasper (Ph: (07) 38298518)
    2.8


    Project life
    Estimated start date of construction: first quarter, 2008
    Estimated life of the project: indefinite
    2.9


    Alternatives No
    X


    Yes, complete section 3.2
    2.10 State

    Link_
    http://www.environment.gov.au/cgi-bin/epbc/epbc_ap.pl?name=show_document;document_id=25012;pr oposal_id=3400

    This will stir the greenies up



  2. #2

    Re: North stradbroke Island Borefeild and Pipline

    it's not only stirring Greenies up, practically every resident is against the plan. there seems to be too many unknowns, not enough conclusive studies. doubt they're even capable of determining long term repercussions.
    What will happen if the hydraulic pressure of the existing ground water is reduced too far? a few of the perched lakes have been dry for years as it is.
    have to find out where they get their crystal balls from.

  3. #3

    Re: North stradbroke Island Borefeild and Pipline

    just find the "educated "person" who declared flat rock a green zone and problem solved no one will be allowed near it.

  4. #4

    Re: North stradbroke Island Borefeild and Pipline

    doesn't redlands already get it's water from straddie?